Opening target: 2030
The new stadium at RFK
Washington is coming home to the RFK campus. Here is every vote, every dollar, the design and the timeline, with sources.
The deal
At least $2.7 billion, covering stadium construction. Councilmember Kenyan McDuffie said cost overruns fall on the team, not D.C.
About $1.1 billion over eight years, as announced in April 2025; WTOP put the city's share at about $1 billion at final approval. It covers $500M toward stadium costs from the sports facilities fee, a $175M revenue bond for parking repaid by stadium activity, $181M from Events DC for parking garages it will own, and $202M for roads and infrastructure, including a WMATA transit study.
The Council's July 2025 revisions added city revenue terms: $414M over 30 years, $260M from non-stadium event parking, a $20M-a-year transportation fund for Metro and roads, and a $50M community benefits agreement.
Sources: wtop.com, wtop.com (2), wtop.com (3)
Timeline
Congress passes the RFK land bill
The bill is the D.C. Robert F. Kennedy Memorial Stadium Campus Revitalization Act (H.R. 4984).
Sources: ksat.com
Biden signs the land transfer
The law gives D.C. control of the RFK campus for 99 years. Jurisdiction moved from the National Park Service to D.C. in January 2025.
Sources: mayor.dc.gov, ksat.com
Old RFK Stadium demolition begins
Work starts in late January 2025, run by Events DC with contractor Smoot Construction.
Sources: ncpc.gov, eventsdc.com
The deal is announced
Mayor Muriel Bowser, owner Josh Harris and NFL Commissioner Roger Goodell announce a 65,000-seat roofed stadium: at least $2.7 billion from the team, about $1.1 billion from D.C., opening target 2030.
Sources: wtop.com
Council misses its deadline and revises the terms
The D.C. Council misses the mid-July deadline. Council leaders then announce revised terms ($414M in city revenue over 30 years, $260M from non-stadium event parking, a $20M-a-year transportation fund) and set votes for Aug. 1 and Sept. 17. The same month, President Trump threatens to hold up the deal unless the team goes back to its former name; nothing came of the threat.
Sources: wtop.com, wtop.com (2)
First Council vote: 9-3
The Council approves the amended deal. No votes: Robert White (At-Large), Brianne Nadeau (Ward 1) and Matthew Frumin (Ward 3).
Sources: wtop.com, wtop.com (2)
Final Council vote: 11-2
Robert White and Brianne Nadeau vote no again; Frumin switches to yes. Many last-minute amendments are voted down before passage.
Sources: wtop.com
HKS named lead architect
The team says vertical construction starts in spring 2027, with completion in 2030.
Sources: commanders.com
First renderings released
The exterior shows a transparent domed roof, a continuous colonnade and room for 70,000-plus people.
Sources: commanders.com, wtop.com
Federal planners weigh in
The National Capital Planning Commission (NCPC) approves its comments on the concept plans.
Sources: ncpc.gov
Fine Arts commission reviews the design
The U.S. Commission of Fine Arts (CFA) reviews the concept design.
Sources: ncpc.gov
NCPC approves preliminary plans
The vote on the site and building plans is unanimous. The two parking garages go through a separate review.
Old stadium structure comes down
Events DC says structural demolition is complete. Removal of foundation walls and columns continues, and about 95% of demolition waste is recycled.
Sources: eventsdc.com
Site preparation begins
The team says site preparation for stadium construction has started.
Sources: wtop.com
Draft campus master plan released
D.C.'s draft plan for the RFK campus calls for 5,500 to 6,500 homes, commercial space and parks across six districts.
Sources: wtop.com
Fine Arts commission gives preliminary approval
The CFA asks for stronger east and west entrances before final review. The plans show a 'Capitol Club' balcony over East Capitol Street.
Sources: sports.yahoo.com, yahoo.com
Builders picked
A joint venture of Clark Construction, Mortenson and Smoot Construction will build the stadium.
Sources: wtop.com
RFK demolition set to wrap up
Events DC targets October 2026 to finish demolition and closeout.
Sources: eventsdc.com
Construction start target
No groundbreaking date set yet. The team says construction begins in 2027: below-grade work in early 2027, vertical construction in spring 2027. Earlier plans had pointed to fall 2026.
Sources: commanders.com, commanders.com (2)
Target opening
The team targets the 2030 season; the builder targets completion in spring 2030.
Sources: wtop.com, wtop.com (2)
What it will have
- Roofed stadium with a sculpted, transparent domed roof for year-round events
- About 1.8 million square feet; about 195 feet tall including the dome
- Continuous colonnade; aligned with the L'Enfant Plan, rising to the north and south and staying lower on the east-west axis in deference to the U.S. Capitol
- One continuous seating bowl from field level to the upper deck: no stacked premium levels, minimal overhangs, steep seating angles, first row raised above the field
- 'Wall of Fans' section with affordable seats
- Video boards on both sidelines plus paired end zone boards, joined by a halo board around the bowl
- Roof and bowl designed to hold crowd noise in; the team says it will be one of the loudest stadiums in the NFL
- 'Capitol Club' balcony over East Capitol Street with views of the Capitol and Washington Monument, first shown in July 2026
- More than 200 events a year planned: games, concerts, festivals
- Up to 8,000 parking spaces at opening: about 75% in two garages up to 110 feet tall, 25% in surface lots
- At least 30% of the site set aside for recreation and green space
- Around the stadium: the 2025 deal set 5,000 to 6,000 homes (1,500 to 1,900 affordable), a new D.C. sportsplex and keeping the existing Fields at RFK. D.C.'s June 2026 draft master plan calls for 5,500 to 6,500 homes
HKS is the lead stadium architect, picked in November 2025. The firm designed SoFi Stadium, U.S. Bank Stadium and AT&T Stadium. Perkins Eastman is planning the mixed-use site around the stadium. A joint venture of Clark Construction, Mortenson and Smoot Construction will build it.
The debate
Public money
D.C.'s share of about $1 billion or more drew criticism. Council Chair Phil Mendelson first said the deal sent very little revenue to the city's general fund; at hearings some residents argued it favored billionaires over housing and social services.
Sources: wtop.com
Housing first
Some locals said they would rather see the land used for housing than another stadium.
Sources: wtop.com
Team name
In July 2025 President Trump threatened to hold up the deal unless the team went back to its former name. Nothing came of it.
Sources: wtop.com, wtop.com (2)
Council dissent
Robert White and Brianne Nadeau voted no twice, citing housing safeguards and public subsidies; Matthew Frumin voted no in August before switching.
Sources: wtop.com, wtop.com (2)
Final-day amendments
On Sept. 17, 2025, council members proposed new taxes on parking and merchandise revenue and penalties for missed housing deadlines. Team president Mark Clouse called the demands 'unworkable and impractical'; the council voted many of them down.
Sources: wtop.com
Traffic and parking
Residents raised congestion and parking impacts on nearby neighborhoods at the 2025 hearings.
Sources: wtop.com
Parking garages
Kingman Park residents oppose two garages up to 11 stories (110 feet) next to their neighborhood and want more Metro capacity instead. NCPC asked the team to study other orientations and lower heights, especially for garage G2 near Kingman Park.
Design review
The Commission of Fine Arts gave preliminary approval in July 2026 but called the east and west entrances too weak for the end of East Capitol Street, and wants more review of the garage plans.
Sources: sports.yahoo.com, yahoo.com
Sources: commanders.com, commanders.com (2), commanders.com (3), commanders.com (4), commanders.com (5), mayor.dc.gov, ksat.com, wtop.com, wtop.com (2), wtop.com (3)
New stadium FAQ
When will the new Commanders stadium open?
The team targets 2030 for the new stadium at the RFK campus in Washington, D.C. Construction is planned to start in spring 2027.
How much does the new Commanders stadium cost?
About $3.7 billion. Announced in April 2025 as 'nearly $4 billion'; WTOP put the approved deal at about $3.7 billion.
How many seats will the new RFK stadium have?
65,000 seats plus standing room for 5,000 (70,000 total)
Who is designing the new Commanders stadium?
HKS is the lead stadium architect, picked in November 2025. The firm designed SoFi Stadium, U.S. Bank Stadium and AT&T Stadium.